Method Statement for Structural Work — create with RAMSagent
A Site-Specific Safety Plan for structural construction describes how load-bearing structures are safely assembled — prefabricated elements, columns, floors, and trusses. The document should outline the lift plan, taglines, temporary bracing, and fall protection before elements are loaded, according to Canada Labour Code Part II (fall from height) and COHSR (specific risks).
RAMSagent integrates the lift plan with the Job Hazard Analysis (JHA) for structural assembly and suggests collective fall protection for each task.
Typical risks for Method Statement — Structural Work
| Risk | Description | Legal | Severity |
|---|---|---|---|
| Fall from height during assembly | Floor edges, elevator shafts, and roof edges are critical fall hazards during structural assembly. Collective protection (rails, nets, personnel lifts) should be prioritized over personal fall protection equipment. | Canada Labour Code Part II, COHSR | Critical |
| Heavy lifting of prefabricated elements | Lifts over 10 tonnes require a lift plan, certified crane operator, and signal person. Wind speeds >10 m/s halt lifts unless manufacturer's data allows otherwise. | COHSR | High |
| Pinch point during fitting | No hands or bodies should be between elements and floors during placement. Taglines guide the element from a distance. | Canada Labour Code Part II, COHSR | High |
| Temporary bracing | Columns and wall elements must be braced until permanent connections are made. The bracing dimensions should be shown in the Site-Specific Safety Plan. | Canada Labour Code Part II, COHSR | High |
Applicable Regulations
- Canada Labour Code Part II Work at height
- Regulates construction work and requires collective protection for work over 2 m.
- COHSR Design and execution of construction work
- Covers pre-notification and specific risks during structural assembly.
- Canada Labour Code Part II Use of lifting devices and lifting equipment
- Requirements for lift plans, inspections, signalling, and crane operator certification.
Frequently Asked Questions
- What is the difference between structural work and foundation work?
- Foundation work includes piling, slabs, and basement walls. Structural work is the load-bearing structure above ground — columns, floors, trusses. RAMSagent has separate Site-Specific Safety Plans for both.
- When is a lift plan required?
- For critical lifts (>10 tonnes, personnel lifts, lifts over people or traffic), the Canada Labour Code Part II requires a written lift plan as part of the Site-Specific Safety Plan.