Priprema radova za stomogradnju opisuje kako se nosiva konstrukcija sigurno montira — prefab elementi, stupovi, ploče i krovne grede. Dokument treba opisivati planove podizanja, uže, privremeno oslanjanje i zaštitu od pada prije nego što se elementi opterete, u skladu sa Zakonom o zaštiti na radu.

RAMSagent integrira planove podizanja s procjenom rizika za montažu konstrukcije i predlaže kolektivnu zaštitu od pada po momentu.

Tipični rizici za Radna uputa — Nosiva konstrukcija

Rizici, opis i primjenjiva pravna osnova
Rizik Opis Pravna osnova Ozbiljnost
Falls from Height During Assembly Floor edges, lift shafts, and roof edges are critical fall edges during structural assembly. Collective protection (guardrails, nets, personnel lifts) should be prioritized over personal fall protection equipment. AFS 2023:11, 15 kap Kritičan
Heavy Lifting of Prefabricated Elements Lifts over 10 tons require a lifting plan, certified crane operator, and signal person. Wind speeds exceeding 10 m/s suspend lifting unless manufacturer's data allows otherwise. AFS 2006:6 Visok
Crush Risk During Fitting No hands or body parts should be between elements and floor slabs during lowering. Tag lines control the element from a distance. AFS 2023:13, 8 kap Visok
Temporary Bracing Columns and wall elements must be braced until permanent connections are made. The sizing of braces should be shown in the method statement. AFS 2023:11, 15 kap Visok
AFS 2023:11 Work at Height
Chapter 15 regulates construction work and requires collective protection for work above 2 meters.
AFS 2023:13 Design and Execution of Construction Work
Covers prior notification and specific risks during structural assembly.
AFS 2006:6 Use of Lifting Equipment and Devices
Requirements for lifting plans, inspections, signaling, and crane operator certification.

Često postavljana pitanja

What is the difference between structural construction and foundation work?
Foundation work includes piling, slabs, and basement walls. Structural construction refers to the load-bearing structure above ground — columns, floor slabs, roof trusses. RAMSagent has separate method statements for both.
When is a lifting plan required?
For critical lifts (>10 tons, personnel lifts, lifts over people or traffic), HSE guidance requires a written lifting plan to be included in the method statement.