A method statement for structural construction describes how load-bearing structures are safely assembled — prefabricated elements, columns, floor slabs, and roof trusses. The document should outline lifting plans, tag lines, temporary bracing, and fall protection before elements are loaded, in accordance with HSE guidance on work at height and CDM 2015 regulations.
RAMSagent integrates lifting plans with risk assessments for structural assembly and suggests collective fall protection for each task.
Riscos típicos para Plano de Trabalho — Estrutura
| Risco | Descrição | Legislação | Gravidade |
|---|---|---|---|
| Falls from Height During Assembly | Floor edges, lift shafts, and roof edges are critical fall edges during structural assembly. Collective protection (guardrails, nets, personnel lifts) should be prioritized over personal fall protection equipment. | AFS 2023:11, 15 kap | Crítica |
| Heavy Lifting of Prefabricated Elements | Lifts over 10 tons require a lifting plan, certified crane operator, and signal person. Wind speeds exceeding 10 m/s suspend lifting unless manufacturer's data allows otherwise. | AFS 2006:6 | Alta |
| Crush Risk During Fitting | No hands or body parts should be between elements and floor slabs during lowering. Tag lines control the element from a distance. | AFS 2023:13, 8 kap | Alta |
| Temporary Bracing | Columns and wall elements must be braced until permanent connections are made. The sizing of braces should be shown in the method statement. | AFS 2023:11, 15 kap | Alta |
Regulamentos aplicáveis
- AFS 2023:11 Work at Height
- Chapter 15 regulates construction work and requires collective protection for work above 2 meters.
- AFS 2023:13 Design and Execution of Construction Work
- Covers prior notification and specific risks during structural assembly.
- AFS 2006:6 Use of Lifting Equipment and Devices
- Requirements for lifting plans, inspections, signaling, and crane operator certification.
Perguntas frequentes
- What is the difference between structural construction and foundation work?
- Foundation work includes piling, slabs, and basement walls. Structural construction refers to the load-bearing structure above ground — columns, floor slabs, roof trusses. RAMSagent has separate method statements for both.
- When is a lifting plan required?
- For critical lifts (>10 tons, personnel lifts, lifts over people or traffic), HSE guidance requires a written lifting plan to be included in the method statement.