Pracovný postup pre Búranie — vytvoriť v RAMSagent

Príprava na demoláciu presne popisuje, ako sa demolácia vykonáva bezpečne — od predbežného prieskumu zdraviu nebezpečných materiálov (azbest, PCB, olovo) po demontáž, triedenie a odvoz. Dokument by mal odkazovať na Zákonník práce a slovenské bezpečnostné predpisy.

RAMSagent generuje kompletné pracovné prípravy pre každú fázu demolácie, vrátane azbestového skríningu, plánu ochrany proti prachu a tried recyklácie — pripravené na tlač alebo zdieľanie s subdodávateľmi.

Typické riziká pre Pracovný postup — Búranie

Riziká, popis a príslušný právny základ
Riziko Popis Právny základ Závažnosť
Asbestos and Other Hazardous Materials Buildings constructed before 1982 may contain asbestos in pipe insulation, facade boards, and floor adhesives. A material inventory is required before demolition, and work can only be performed with permission and medical monitoring. AFS 2023:10, 16 kap; AFS 2005:6 Kritická
Respirable Crystalline Silica (RCS) Demolition of concrete, brick, and plaster releases respirable crystalline silica (RCS) which causes silicosis and lung cancer. The exposure limit of 0.1 mg/m³ requires water suppression or H-class vacuuming. AFS 2023:10, 3 kap Vysoká
Fall Risks During Partial Demolition When floors are demolished in stages, edges, stair openings, and lift shafts become temporary fall edges. Collective protection (guardrails, nets) must be re-established before work continues above 2 m. AFS 2023:11, 15 kap Kritická
Crushing Risks During Machine-Controlled Demolition Excavators with demolition shears require exclusion zones of at least 1.5 times the machine's reach. No one is allowed in the risk area during demolition. AFS 2023:13, 8 kap Vysoká
AFS 2023:13 Planning and Execution of Construction and Demolition Work
Framework regulations for construction sites, including demolition. Requires coordination, notification, and safety responsibilities.
AFS 2023:10 Chemical Workplace Risks
Regulates silica dust, asbestos, and other hazardous substances released during demolition. Requires risk assessment, measurement, and action plans.
AFS 2005:6 Medical Surveillance in the Workplace
Medical surveillance is required for personnel working with asbestos-containing materials.

Často kladené otázky

Is an asbestos inventory required before demolition?
Yes — for all buildings constructed before 1982 (and often later), HSE guidance requires a material inventory before demolition. RAMSagent reminds users of the inventory in the method statement and links it to the required asbestos remediation.
When is notification required for demolition?
Notification to the HSE is required when the work is expected to last more than 30 working days with more than 20 simultaneous workers, or more than 500 person-days.